Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also, find the total elapsed time:

Jobs I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6
योग
Advertisements

उत्तर

Jobs Time (in hours)
Lathe (A) Surface grinder (B)
I 4 3
II 1 2
III 5 4
IV 2 3
V 5 6

Here, min(A, B) = 1, which corresponds to A. 

Therefore, job II is processed first.

II        

The problem now reduces to jobs I, III, IV, and V.

Here, Min.(A, B) = 2, which corresponds to A.

Therefore, job IV is processed next to job II.

II IV      

The problem now reduces to jobs I, III, and V.

Here, Min. (A, B) = 3, which corresponds to B

Therefore, job I is processed at the last.

II IV     I

The problem now reduces to jobs III and V.

Here, Min. (A, B) = 4, which corresponds to B.

Therefore, job III is processed at the last, next to job I

II IV   III I

Now, job V is processed next to job IV, and we get the optional sequence of jobs as follows:

II IV V III I

Total elapsed time is obtained as follows:

Jobs Sequence Lathe (A) Surface grinder (B)
Time in Time out Time in Time out
II 0 1 1 3
IV 1 3 3 6
V 3 8 8 14
III 8 13 14 18
I 13 17 18 21

Total elapsed time T = 21 hours.