Advertisements
Advertisements
प्रश्न
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also, find the total elapsed time:
| Jobs | I | II | III | IV | V |
| Lathe | 4 | 1 | 5 | 2 | 5 |
| Surface grinder | 3 | 2 | 4 | 3 | 6 |
Advertisements
उत्तर
| Jobs | Time (in hours) | |
| Lathe (A) | Surface grinder (B) | |
| I | 4 | 3 |
| II | 1 | 2 |
| III | 5 | 4 |
| IV | 2 | 3 |
| V | 5 | 6 |
Here, min(A, B) = 1, which corresponds to A.
Therefore, job II is processed first.
| II |
The problem now reduces to jobs I, III, IV, and V.
Here, Min.(A, B) = 2, which corresponds to A.
Therefore, job IV is processed next to job II.
| II | IV |
The problem now reduces to jobs I, III, and V.
Here, Min. (A, B) = 3, which corresponds to B
Therefore, job I is processed at the last.
| II | IV | I |
The problem now reduces to jobs III and V.
Here, Min. (A, B) = 4, which corresponds to B.
Therefore, job III is processed at the last, next to job I
| II | IV | III | I |
Now, job V is processed next to job IV, and we get the optional sequence of jobs as follows:
| II | IV | V | III | I |
Total elapsed time is obtained as follows:
| Jobs Sequence | Lathe (A) | Surface grinder (B) | ||
| Time in | Time out | Time in | Time out | |
| II | 0 | 1 | 1 | 3 |
| IV | 1 | 3 | 3 | 6 |
| V | 3 | 8 | 8 | 14 |
| III | 8 | 13 | 14 | 18 |
| I | 13 | 17 | 18 | 21 |
Total elapsed time T = 21 hours.