A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. - CBSE Class 10 - Mathematics

Login
Create free account


      Forgot password?

Question

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days.

Solution

It can be observed that these penalties are in an A.P. having first term as 200 and common difference as 50.

a = 200

d = 50

Penalty that has to be paid if he has delayed the work by 30 days = S30

`= 30/2[2(200)+(30-1)50]`

= 15 [400 + 1450]

= 15 (1850)

= 27750

Therefore, the contractor has to pay Rs 27750 as penalty.

  Is there an error in this question or solution?

APPEARS IN

 NCERT Solution for Mathematics Textbook for Class 10 (2019 to Current)
Chapter 5: Arithmetic Progressions
Ex. 5.30 | Q: 15 | Page no. 113
Solution A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. Concept: Sum of First n Terms of an AP.
S
View in app×