Solve the following question and mark the best possible option.
It takes 8 people working at equal rates to finish work in 96 days. How long will 6 workers take to finish the same work?

Options

  • 92 days

  • 128 days

  • 111 days

  • 84 days

Advertisement Remove all ads

Solution

128 days

Explanation:

Required number of days = 96 x `8/6` = 128 days.