Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solution
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
Observe that Min (lathe, grinder) = 1, corresponds to job II on lathe.
∴ Job II is placed first in sequence.
II |
Then the problem reduces to
Job | I | III | IV | V |
Lathe | 4 | 5 | 2 | 5 |
Surface grinder | 3 | 4 | 3 | 6 |
Now, Min (lathe, grinder) = 2, corresponds to job IV on lathe.
∴ Job IV is placed after II in sequence.
II | IV |
Then the problem reduces to
Job | I | III | V |
Lathe | 4 | 5 | 5 |
Surface grinder | 3 | 4 | 6 |
Now, Min (lathe, grinder) = 3, corresponds to job I on grinder.
∴ Job I is placed last in sequence.
II | IV | I |
Then the problem reduces to
Job | III | V |
Lathe | 5 | 5 |
Surface grinder | 4 | 6 |
Now, Min (lathe, grinder) = 4, corresponds to job III on grinder.
∴ Job III is placed before I and V on remaining in sequence.
∴ Optimal sequence is
II | IV | V | III | I |
Total elapsed time
Job | Lath | Surface Grinder |
||
In | Out | In | Out | |
II (1, 2) | 0 | 1 | 1 | 3 |
IV (2, 3) | 1 | 3 | 3 | 6 |
V (5, 6) | 3 | 8 | 8 | 14 |
III (5, 4) | 8 | 13 | 14 | 18 |
I (4, 3) | 13 | 17 | 18 | 21 |
∴ Total elapsed time = 21 hrs
Idle time for lathe = 21 – 17 = 4 hrs
Idle time for surface grinder = 1 + 2 = 3 hrs.