Tamil Nadu Board of Secondary EducationSSLC (English Medium) (5 to 8) Class 8

P alone can do 12 of a work in 6 days and Q alone can do 23 of the same work in 4 days. in how many days will they finish 34 of the work, working together? - Mathematics

Advertisements
Advertisements
Sum

P alone can do `1/2` of a work in 6 days and Q alone can do `2/3` of the same work in 4 days. in how many days will they finish `3/4` of the work, working together?

Advertisements

Solution

`1/2` of the work is done by P in 6 days

∴ Full work is done by P in `6/(1/2)` = 6 × 2 = 12 days

`2/3` of work done by Q in 4 days.

∴ Full work is done by Q in `4/(2/3) = 4 xx 3/2` = 6 days

(P + Q) will finish the whole work in `"ab"/("a" + "b")` days

= `(12 xx 6)/(12 + 6)`

= `(12 xx 6)/18`

= 4 days

(P + Q) will finish `(-3)/4` of the work in `4 xx 3/4` = 3 days.

Concept: Time and Work
  Is there an error in this question or solution?
Chapter 4: Life Mathematics - Exercise 4.5 [Page 152]

APPEARS IN

Tamil Nadu Board Samacheer Kalvi Class 8th Mathematics Answers Guide
Chapter 4 Life Mathematics
Exercise 4.5 | Q 14 | Page 152

RELATED QUESTIONS

In a fort 150 men had provisions for 45 days. After 10 days, 25 men left the fort. How long would the food last at the same rate?


If 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours?


A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal has been completed. How many more men must be employed to finish the work on time?


A can do a piece of work in 10 days and B in 15 days. How long will they take together to finish it?


A and B together can do a piece of work in `6 2/3` days, but B alone can do it in 10 days. How long will A take to do it alone?


A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?


A and B working together can mow a field in 56 days and with the help of C, they could have mowed it in 42 days. How long would C take by himself?


A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B, and C together finish it in 18 days. In how many days will:
(i) A alone,
(ii) C alone,
(iii) A and C together, complete the work?


A and B can do a piece of work in 40 days; B and C in 30 days; and C and A in 24 days.
(i) How long will it take them to do the work together?
(ii) In what time can each finish it working alone?


Two pipes P and Q would fill an empty cistern in 24 minutes and 32 minutes respectively. Both the pipes being opened together, find when the first pipe must be turned off so that the empty cistern maybe just filled in 16 minutes.


P and Q can do a piece of work in 12 days and 15 days respectively. P started the work alone and then after 3 days, Q joined him till the work was completed. How long did the work last?


X alone can do a piece of work in 6 days and Y alone in 8 days. X and Y undertook the work for ₹ 48000. With the help of Z, they completed the work in 3 days. How much is Z’s share?