For the following problem, find the sequence that minimizes total elapsed time (in hours) required to complete jobs on two machines M1 and M2 in the order M1-M2 Also find the minimum elapsed time T. - Mathematics and Statistics

Advertisement Remove all ads
Advertisement Remove all ads
Advertisement Remove all ads

For the following problem, find the sequence that minimizes total elapsed time (in hours) required to complete jobs on two machines M1 and M2 in the order M1-M2 Also find the minimum elapsed time T.

Jobs

A

B

C

D

E

Machine M1

5

1

9

3

10

Machine M2

2

6

7

8

4

Advertisement Remove all ads

Solution

 

Given :

Jobs

A

B

C

D

E

Machine M1

5

1

9

3

10

Machine M2

2

6

7

8

4

finding the optimal sequence :

The minimum processing time on two machines is 1 which correspond to task B on machine M1. This shows that task B will be preceding first. After assigning task B, we are left with 4 tasks on two machines

 

Jobs

A

C

D

E

Machine M1

5

9

3

10

Machine M2

2

7

8

4

 

B        

Minimum processing time in this reduced problem is 2 which correspond to job A on machine M2 therefore task A will be processed in the last.

B       A

The problem now reduces to following 3 tasks on two machines with processing time as follows:

Jobs

C

D

E

Machine M1

9

3

10

Machine M2

7

8

4

Minimum processing time in this reduced problem is 3 which correspond to job D on machine M1 therefore task D will be processed in the next to B.

B D     A

The problem now reduces to following 2 tasks on two machines with processing time as follows:

Jobs

C

E

Machine M1

9

10

Machine M2

7

4

Minimum processing time in this reduced problem is 4 which correspond to job E on machine Mtherefore task E will be processed in the next to last.

B D C E A

Further, it is also possible to calculate the minimum elapsed time corresponding to the optimal sequencing B→D→C→E→A

Job Sequence

Machine M1

Machine M2

 

Time In

Time Out

Time In

Time Out

B

0

1

1

7

D

1

4

7

15

C 4 13 15 22
E 13 23 23 27
A 23 28 28 30

 

Hence the total elapsed time for this proposed sequence  staring from job B to completion of job A is 30 hours .During this time machine M1 remains idle for 2 hours and the machine M2 remains idle for 3 hours

Minimum time elapse : 30 Hours

 

Concept: Sequencing in Management Mathematics
  Is there an error in this question or solution?
2014-2015 (March)

APPEARS IN

Share
Notifications

View all notifications


      Forgot password?
View in app×