Choose the correct alternative :
If job A to D have processing times as 5, 6, 8, 4 on first machine and 4, 7, 9, 10 on second machine then the optimal sequence is :
Options
CDAB
DBCA
BCDA
ABCD
Advertisement
Solution
If job A to D have processing times as 5, 6, 8, 4 on first machine and 4, 7, 9, 10 on second machine then the optimal sequence is : DBCA.