Choose the correct alternative : If job A to D have processing times as 5, 6, 8, 4 on first machine and 4, 7, 9, 10 on second machine then the optimal sequence is : - Mathematics and Statistics

Advertisement Remove all ads
Advertisement Remove all ads
MCQ

Choose the correct alternative :

If job A to D have processing times as 5, 6, 8, 4 on first machine and 4, 7, 9, 10 on second machine then the optimal sequence is :

Options

  • CDAB

  • DBCA

  • BCDA

  • ABCD

Advertisement Remove all ads

Solution

If job A to D have processing times as 5, 6, 8, 4 on first machine and 4, 7, 9, 10 on second machine then the optimal sequence is : DBCA.

Concept: Finding an Optimal Sequence
  Is there an error in this question or solution?
Advertisement Remove all ads

APPEARS IN

Balbharati Mathematics and Statistics 2 (Commerce) 12th Standard HSC Maharashtra State Board
Chapter 7 Assignment Problem and Sequencing
Miscellaneous Exercise 7 | Q 1.02 | Page 126
Advertisement Remove all ads
Share
Notifications

View all notifications


      Forgot password?
View in app×