Advertisement Remove all ads

A contractor Abhay Singh employed some men to do a piece of work which can be done by 16 men in 14 days. At the end of 5 days, 7 of the men stopped working and 3 days later half of the remainder - Mathematics

MCQ

A contractor Abhay Singh employed some men to do a piece of work which can be done by 16 men in 14 days. At the end of 5 days, 7 of the men stopped working and 3 days later half of the remainder stopped working; the rest finished the work in 5 days. What is the number of men originally employed?

Options

  • 25

  • 27

  • 29

  • 33

Advertisement Remove all ads

Solution

25

Explanation:

16 men can complete the work in 14 days

Let initially x men were employed

using M1D1 = M2D2

ATQ

`16xx14=5"x"+3("x"-7)+5(("x"-7))/2`

`224=(21"x"-42-35)/2`

21x = 448 + 77

`"x"=525/21=25`

Concept: Time and Work (Entrance Exam)
  Is there an error in this question or solution?
Advertisement Remove all ads
Advertisement Remove all ads
Share
Notifications

View all notifications


      Forgot password?
View in app×