A contractor Abhay Singh employed some men to do a piece of work which can be done by 16 men in 14 days. At the end of 5 days, 7 of the men stopped working and 3 days later half of the remainder - Mathematics

Advertisements
Advertisements
MCQ

A contractor Abhay Singh employed some men to do a piece of work which can be done by 16 men in 14 days. At the end of 5 days, 7 of the men stopped working and 3 days later half of the remainder stopped working; the rest finished the work in 5 days. What is the number of men originally employed?

Options

  • 25

  • 27

  • 29

  • 33

Advertisements

Solution

25

Explanation:

16 men can complete the work in 14 days

Let initially x men were employed

using M1D1 = M2D2

ATQ

`16xx14=5"x"+3("x"-7)+5(("x"-7))/2`

`224=(21"x"-42-35)/2`

21x = 448 + 77

`"x"=525/21=25`

Concept: Time and Work (Entrance Exam)
  Is there an error in this question or solution?

RELATED QUESTIONS

Arun can climb a Coconut tree by 1.5 feet by each lift; however, he slips 0.5 feet every time he makes the next lift. How many individual lifts he will have to reach the top of the Coconut tree of 18.5 feet?


Choose the most appropriate option

‘A’ and ‘B’ complete a work in 12 days, ‘B’ and ‘C’ in 8 days and ‘C’ and ‘A’ in 16 days. ‘A’ left after working for 3 days. In how many days more will ‘B’ and ‘C’ finish the remaining work?


Choose the most appropriate option.

A can do a piece of work in 8 days and B alone can do the same work in 10 days. A and B agreed to do the work together for Rs. 720. With the help of C, they finished the work in 4 days. How much C is to be paid?


Choose the most appropriate option.

Two men and seven boys can do work in 14 days. Three men and eight boys can do the same work in 11 days. Further, eight men and six boys can do three times the amount of this work in:


Solve the following question and mark the best possible option.
It takes 8 people working at equal rates to finish work in 96 days. How long will 6 workers take to finish the same work?


A group of workers accepted to do a piece of work in 25 days. If 6 of them did not turn up for the work and the remaining workers did the work in 40 days, then the original number of workers was


A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?


A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in


A water tank has three taps A, B and C. A fills four buckets in 24 minutes, B fills 8 buckets in 1 hour and C fills 2 buckets in 20 minutes. If all the taps are opened together a full tank is emptied in 2 hours. If a bucket can hold 5 litres of water what is the capacity of the tank?


A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?


A does 80% of work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?


If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be


Twenty women can do a piece of work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?


A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work, if he is assisted by B and C on every third day?


A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for ₹ 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?


A, B, and C get  ₹5400 for doing work in 36 days. A and C get ₹1880 for doing the same work in 20 days, which B and C get ₹3040 for doing the same work in 40 days. Find the amount received by C per day.


Two pipes P and Q can fill a tank in 15 min and 20 min, respectively. Both the pipes are opened together but after 4 min, pipe P is turned off. What is the total time required to fill the tank?


15 men can do a work in 20 days. If there are 25 men, how many days will it take to complete the work?


A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:


8 boys and 12 girls together can finish a project work in 5 days. If it takes 50 days for one boy alone to finish the same project, how many days are required for one girl alone to complete the same project work?


A fort had provision for 400 men for 60 days. After 35 days, 100 more men came. For how many days would the provisions last, assuming all men consumed food equally?


A can do a work in 6 days and B in 9 days. How many days wlll both take together to complete the work?


A. B and C together can complete a piece of work in 30 minutes. A and B together can complete the same work in 50 minutes. C alone can complete the work in ______.


Anil can do a job in 10 days. Sunn is 40% more efficient than Anil. Find the no. of days required by Sunil to do the same job.


8 men can finish half of the work in 3 days. If the remaining work is to be completed in 2 days. then the no. of additional men required are?


15 men and 7 women can mow a field in 10 days. In how many days can 30 men and 14 women mow a field thrice as big as the previous one?


26 men can complete a piece of work in 17 days. How many more men must be hired to complete the work in 13 days?


Five men can complete a piece of work in 24 days. In how many days will 12 men complete the same piece of work?