A and B Can Do a Piece of Work in 6 and 12 Days, Respectively. They (Both) Will Complete the Work in How Many Days? - Mathematics

Advertisements
Advertisements
MCQ

A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?

Options

  • 9 days

  • 18 days

  • 6 days

  • 4 days

Advertisements

Solution

4 days

Explanation:

A's 1 day's work = `1/6`

B's 1 day's work = `1/12`

(A+ B)'s 1 day's work = `1/6+1/12`

= `(2+1)/12=3/12=1/4`

Hence, both will complete the work in 4 days.

Second Method

Here, x = 6

and y = 12

∴ Time taken by (A+ B) = `(xy)/(x+y)`

= `(6xx12)/(12+6)` = 4 days

Concept: Time and Work (Entrance Exam)
  Is there an error in this question or solution?

RELATED QUESTIONS

Arun can climb a Coconut tree by 1.5 feet by each lift; however, he slips 0.5 feet every time he makes the next lift. How many individual lifts he will have to reach the top of the Coconut tree of 18.5 feet?


Choose the most appropriate option.

A can do a piece of work in 8 days and B alone can do the same work in 10 days. A and B agreed to do the work together for Rs. 720. With the help of C, they finished the work in 4 days. How much C is to be paid?


Twenty-five workers were employed to complete a compound wall in 12 days. Five workers left after working for 4 days. The remaining 20 workers completed the work. In how many days the total job was completed?


16 men can do a piece of work in 16 days. 4 days after they started the work 8 more men joined them. How many days will they now take to complete the remaining work?


A contractor Abhay Singh employed some men to do a piece of work which can be done by 16 men in 14 days. At the end of 5 days, 7 of the men stopped working and 3 days later half of the remainder stopped working; the rest finished the work in 5 days. What is the number of men originally employed?


A group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?


A water tank has eight pipes fitted into it. Pipes are of two types: Green Pipe and Red Pipe. Green pipes are used to fill the tank and the Red pipes are used to empty the tank. Every Green pipe can fill the tank in 12 hours and every Red pipe can empty it in 36 hours. On opening all the pipes an empty tank is filled in 3 hours. The number of Red pipe is


A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?


A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in


Aarti can do a piece of work in 6 days. In how many days will she complete three times of work of the same type?


A water tank has three taps A, B and C. A fills four buckets in 24 minutes, B fills 8 buckets in 1 hour and C fills 2 buckets in 20 minutes. If all the taps are opened together a full tank is emptied in 2 hours. If a bucket can hold 5 litres of water what is the capacity of the tank?


A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?


4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days, will 10 women complete it?


A and B can together finish work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days, A alone can finish the work?


A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work, if he is assisted by B and C on every third day?


A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for ₹ 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?


A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for ₹5400. They begin the work together but B left 2 days before the completion of work and C left 5 days before the completion of work. The share of A from the assured money is


A, B, and C get  ₹5400 for doing work in 36 days. A and C get ₹1880 for doing the same work in 20 days, which B and C get ₹3040 for doing the same work in 40 days. Find the amount received by C per day.


Ram can do a work in 60 days and the same work Sohan can finish in 40 days. If both of them work together, then in how many days will the work be over?


A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:


Vikas can complete a job in 15 days. Babin can do the same job in 10 days. In how many days can they complete the job if they work together?


A fort had provision for 400 men for 60 days. After 35 days, 100 more men came. For how many days would the provisions last, assuming all men consumed food equally?


Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days?


5 men can do a piece of work in 6 days while 10 women can do it in 5 days. In how many days can 5 women and 3 men do it?


15 men and 7 women can mow a field in 10 days. In how many days can 30 men and 14 women mow a field thrice as big as the previous one?


A project manager hired 16 men to complete a project in 38 days. However, after 30 days, he realized that only `5/9`th of the work is complete. How many more men does he need to hire to complete the project on time?


B is `4/3` times as efficient as A. If A can complete `5/8`th of a given task in 15 days, what fraction of the same task would remain incomplete if B works on it independently for 10 days only?