8 men can do a piece of work in 9 days. In how many days will 6 men do it?

 

Solution

\[\text{ It is given that 8 men can complete a job in 9 days }  . \]
\[ \therefore \text{ Time taken by 1 man to complete the same job }  = \left( 8 \times 9 \right) = 72 \text{ days } \]
\[ \therefore \text{ Time taken by 6 men to complete the same job } = \frac{72}{6} = 12 \text{ days } \]

  Is there an error in this question or solution?
Solution 8 Men Can Do a Piece of Work in 9 Days. in How Many Days Will 6 Men Do It? Concept: Time and Work.